Tools required: Knife | Straight Edge | Tape Measure
|
|
|
||||||||||||||||||||||||||||||
|
Note:
New construction installations should be performed only after the building is completely enclosed and the climate control system is in operation for a minimum of two weeks. In geographic regions where concrete slabs may be subject to higher moisture levels, a calcium chloride test is required. Vapour emission readings in excess of 3 lbs/1000 sq ft in less than 24 hours will require additional protection such as a concrete sealant, moisture abatement, or a 6 mil polyethylene sheeting. |
||||||||||||||||||||||||||||||||